Work continues at CCES

Roof repairs continue at the Elementary School. This week, the contractor personnel uncovered a large area over the restrooms that appeared to be in bad condition with separating seams in the roofing sheets. We are surprised that this area hasn't had significant leaks in the past. The contractor will be repairing these areas and applying a continuous coating material over the entire area to extend the life of the existing roof. Also, flashings around the gym roof have been extended further down the wall to stop rain from blowing in under the old flashings.

The contractors have begun work on repairing foundations at the Elementary School. This work involves excavating to the bottom of building footings in certain areas and installing deep steel piers to provide additional support to those areas that have exhibited some settlement or wall movement in the past. Work will continue for at least a week; possibly longer if predicted rains occur later this week.